KARACHI, Feb 28: With a view to making a signal-free road from SITE to Quaid-i-Azam International Airport, the city government has decided to initiate half a dozen major development works, simultaneously from first week of March, the city Nazim Syed Mustafa Kamal said on Tuesday.

These vital projects include flyovers at University Road-Sir Shah Suleman Road traffic intersection (Hasan Square), Pir Sibghatullah Shah Rashdi Road-Stadium Road intersection, near Time Medicos; and Ibrahim Rahimtoola Road-Sharea Faisal traffic intersection (Karsaz) and underpasses at Gharibabad, Nazimabad petrol pump and Liaquatabad No 10.

All these six plans would ensure signal-free movement of traffic from SITE to Quaid-i-Azam International Airport’, the city nazim said.

At a joint a joint meeting of the CDGK and KWSB engineers, contractors and representatives of consulting firms, the nazim stated that work on all the six components of the project must begin in the first week of March and accomplish simultaneously within their stipulated period. The CDGK’s district coordination officer, Fazal-ur-Rehman and the KWSB managing director, Brig Iftikhar Haider were also present.

He said since funds for the project had been provided and the issue pertaining to shifting of utility pipelines had been resolved, contractors and consultants would have no excuse for delaying the project.

Exhorting the CDGK’s consulting firms and contractors to further improve their performance, Mr Kamal said that consulting firms are required to have a check on contractors and give proper advice to officials of the CDGK’s department concerned.

The Nazim urged the contractors and consultants to carry out work on all the six components of the project round-the-clock so that the project is completed expeditiously because if work on any of the six development works is delayed, the entire project would suffer and the citizens will face hardship.

He said he would honour his commitment concerning payments to contractors, but at the same time said he would expect from both the contractors and the consultants to accomplish projects within their stipulated period.

Opinion

Editorial

Border clashes
19 May, 2024

Border clashes

THE Pakistan-Afghanistan frontier has witnessed another series of flare-ups, this time in the Kurram tribal district...
Penalising the dutiful
19 May, 2024

Penalising the dutiful

DOES the government feel no remorse in burdening honest citizens with the cost of its own ineptitude? With the ...
Students in Kyrgyzstan
Updated 19 May, 2024

Students in Kyrgyzstan

The govt ought to take a direct approach comprising convincing communication with the students and Kyrgyz authorities.
Ominous demands
Updated 18 May, 2024

Ominous demands

The federal government needs to boost its revenues to reduce future borrowing and pay back its existing debt.
Property leaks
18 May, 2024

Property leaks

THE leaked Dubai property data reported on by media organisations around the world earlier this week seems to have...
Heat warnings
18 May, 2024

Heat warnings

STARTING next week, the country must brace for brutal heatwaves. The NDMA warns of severe conditions with...